Structural beams strengthening on 7th floor by carbon plate and carbon wrap

We selected strengthening by carbon fiber plate and carbon fiber wrap with reference to location of additional loads and existing layout of RC Beams.


A. Existing Structure Description:  


As the Structural Engineers for The Victoria Commercial Bank building at Two Rivers,  Ruaka, Nairobi, we have designed the building with 800x400mm beams and 175mm  thick RC solid slabs. Total of Dead load and Imposed loads is 17KN/m2 taking into  account light weight infill partition walls.  Victoria Commercial Bank is in process of fitting out for new branch on 7th Floor. Heavy  equipment such as Lockers, Strong Room door and Mantrap and CIT unit will be placed  on the floor slab. The Strong Room and Locker Rooms is built with 200mm thick stone  walls and secured with heavy 4mm thick MS steel plates all around. These additional  weights are not considered during initial design, therefore; external strengthening of the  structure at specific locations has been implemented.  We selected strengthening by carbon plate with reference to location of additional loads  and existing layout of RC Beams.  


B. Photographs with Description  


The following photographs with brief descriptions explain the stages of the Carbon Fiber Plate and Carbon Wrap Process:  


1.jpg

Photo 1: Site preparation including covering all the walls & exposed surfaces with PVC sheets to  protect against damage

2.jpg

Photo 2: Props were put up before carbon plating works were started as internal partition works  were started.  

3.jpg

Photo 3: Surface Preparation which involved removal of paint & the skimming coat on the RC  beams by Sanding and Grinding.

Carbon Laminates (Plates) on the RC Beam

Photo 4: Application of epoxy resin & fixing of Carbon Laminates (Plates) on the RC Beam  soffits for tensile strengthening.  

5.jpg

Photo 5: Supporting the applied Carbon Laminates with formwork for proper bonding.

Carbon Fiber Wraps for RC beams

Photo 6: Application of epoxy resin in preparation for installation of Carbon Fiber Wraps around  the soffits of the down-stand RC beams for Shear strengthening

RC Beams Carbon Fiber Wraps

Photo 7: Marking around on the soffits of the RC Beams for installation of Carbon Fiber Wraps.

Fixed Carbon Laminates (Plates) On Beam

Photo 8: Fixed Carbon Laminates (Plates) on 7th Floor slab on Top of the RC Beam for resisting  Negative Bending Moment Deflection which can cause hogging.  

Carbon Laminates On RC Beam

Photo 9: Fixed Carbon Laminates (Plates) on 7th Floor slab on Top of the RC Beam for resisting  Negative Bending Moment Deflection which can cause hogging. Note, partition walls had to be  cut to for continuous passing of Carbon Laminates.

Carbon Plating and Carbon Wrapping

Photo 10: On going Carbon Plating and Carbon Wrapping works. Note supporting props and  form work to allow curing of epoxy glue. Propping was done intermittently as per progress of  works.

Carbon Fiber Warp for enhanced  strength

Photo 11: Main Curved Primary Bean completely covered with Carbon Fiber Warp for enhanced  strength

installation of Fiber Laminates and Carbon Fiber Wraps bonded onto the RC  Beams

Photo 12: Photo away from Glass Wall: Completed Carbon Plating and Carbon Wrapping Works  which involved installation of Fiber Laminates and Carbon Fiber Wraps bonded onto the RC  Beams using Epoxy Resin as the adhesive and acting as external reinforcements to aid in  accommodating extra loading on the 7th floor.  

Fiber Laminates and Carbon Fiber Wraps bonded onto the RC  Beams using Epoxy Resin

Photo 13: Photo towards Glass Wall: Completed Carbon Plating and Carbon Wrapping Works  which involved installation of Fiber Laminates and Carbon Fiber Wraps bonded onto the RC  Beams using Epoxy Resin as the adhesive and acting as external reinforcements to aid in  accommodating extra loading on the 7th floor.


Conclusion:  


External strengthening of the structure at specific locations has been implemented.


We recommended structural strengthening of the existing beams by Carbon Plating and Carbon  Wrapping and selected ULTRATECH Building Solution Limited to execute the Carbon Plating  and Carbon Wrapping Works. Carbon Plating and Carbon Wrapping is the use of carbon fiber  laminates and carbon fiber wraps, bonding onto the beam using epoxy resin as the adhesive and  acts as external reinforcement.


Where the heavy equipment will be located, the extra dead load is 6KN/m2 . The following  5Nos. of beams have been strengthened to take the extra loading.  


Tbm 1 800x250mm  Tbm 2a 800x400mm  Tbm 3a 800x400mm  Tbm 4 800x400mm  Tbm 7 800x400mm  


The External Strengthening of the Structure at selected locations has been done successfully as  per requirement.  


Following is the Table provides the data to support Carbon Plate Design Works.


carbon plate for retrofitting


Attachments:


Attached are the following Structural Drawings and Product Data Sheets:


A. Structural Drawing For 7th Floor Carbon Plating Works:  


1. Drawing No.: BA/VCB/TR/0120/L12 Rev K: 7th Floor Layout Showing Beams for  Carbon Plating.  


2. Drawing No.: BA/VCB/TR/0120/CP: 7th Floor Beams For Carbon Plating


B. Data Sheets for Carbon Plates and Carbon Fiber used:


1. HM-1.2T Carbon Fiber Plate 

2. HM-30 Carbon Fiber Fabric 

3. Carbon Fiber Fabric - Horse Construction

Carbon Fiber Fabric - Horse Construction

The products used in this casePeople who browsed this project also concern these products:

Back
Top
Close